Allerton Waste Recovery Park

I paid a visit to our Allerton Waste Recovery Project in North Yorkshire last week to see first hand the progress that is being made.  The project is an EfW (Energy from Waste) plant with additionally a MT (Mechanical Treatment) facility and a bottom ash) handling facility.

The client for the project is AMEY and the EfW plant is being delivered by VINCI Environment UK.  VEUK incorporates Taylor Woodrow – a division of Vinci Construction UK – who are delivering the civil works and Vinci Environment France who are delivering the process and M&E works.  You can find out all about the facility on AMEY’s dedicated website at www.allerton-waste-recovery-park.co.uk. Via the website you can also view a live webcam image of the site from the camera mounted on the site offices.

110713-3d-viewVisualisation of the completed plant.  EfW far centre. MT near left. BA right.

Work is currently centered on the concrete works with elements of the steel frame starting soon.  Early next year will see the process equipment installation commencing with remaining concrete works and steelwork installation continuing alongside.

Included below are a few photos from around the site.  All open into new windows when clicked.

DSC_4902
General view of EfW plant
DSC_4908
Concreting an upper wall of the EfW waste reception bunker
DSC_4923
Concreting an upper wall of the EfW waste reception bunker
DSC_4929
Area between the EfW bunker and the turbine hall. The furnaces will be in this area
DSC_4933
Side view the EfW bunker
DSC_4935
Rear view of the MT reception bunker. These fins will support the chutes into the bunker.
DSC_4939
Front view of the MT bunker under construction
DSC_4952
Wide view of EfW plant under construction.
DSC_4953
Pad foundations for the end wall of the MT plant building.
DSC_4977
View from rear of EfW Bunker. Trucks will discharge from a level around the top of the part constructed wall in the foreground from the tipping hall area which will be constructed after the bunker is complete.
DSC_4983
Rear view of the MT bunker under construction
DSC_4991
EfW bunker under construction

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: